Registry Search Mobile

Registry Search

Sandy Bay First Nation New Water Treatment Plant

Sandy Bay First Nation New Water Treatment Plant

Project Summary: Sandy Bay Ojibway First Nation (SBOFN) Reserve No. 283 is located on the south
basin of Lake Manitoba in the Westlake Region of Manitoba, 120 km northwest of Winnipeg and 60 km
northwest of Portage la Prairie. The reserve is accessed by an all-weather provincial road grid system via
PTH 50. SBOFN has a total registered population of 6,781 people. The estimated on reserve population
including both registered and unregistered persons is 4,909. The reserve contains 601 residences and 30
FN owned buildings and facilities. The existing treatment system does not comply with applicable
guidelines including the ISC, Health Canada, or Manitoba Provincial requirements for surface water
treatment. Furthermore, the system requires additional storage capacity to meet future community
demands, provide for the fire protection needs, and meet the disinfection requirements for a surface
water source. The proposed project includes construction of a new Water Treatment Plant (WTP),
installation of a new raw water intake pipe and screen into Lake Manitoba, zebra mussel control system
for the raw water intake system, new raw water intake pumphouse and intake line to the WTP, one new
remote truckfill, one retrofitted truckfill, new water supply line rom the WTP to the school, and
connections to the existing distribution and sewer system for the community. The existing WTP, school
pumphouse, and westend pumphouse will be decommissioned. The new truckfill is proposed to be
located at the corner of South Boundary road and South Ridge road complete with a reservoir to provide
convenience for trucked delivery and reduce traffic in the core area. Whereas the retrofitted truckfill is
proposed to be located at the soon to be decommissioned existing WTP, intended to service to the
homes in the northern portion of the reserve.

Infrastructure: The new WTP will require a new building within the community adjacent the arena,
community centre, and school. A new raw water intake and screen into Lake Manitoba will be required.
The new raw water supply line will be routed alongside an existing road to the new WTP. It is proposed
that the new intake line be placed in the vicinity of the existing intake which is proposed to be capped
(to be confirmed at detailed design) and will include a zebra mussel chemical control system and copper
fish screen (DFO compliant). Power will be provided through the existing electrical lines with new
electrical service provided at the WTP via existing 3-phase service available by the Arena located
adjacent to the project site. The existing distribution lines within the community will be incorporated in
the project with new connections including: connection of the WTP distribution line to existing,
connection to the school and connection to the new truckfill. A connection and line to the existing
sewage lagoon via a manhole will be added to discharge of WTP process wastewater. A new truckfill
station complete with a reservoir is also proposed.

Activities: Planning: SBOFN has conducted a feasibility study and design is currently underway. The
planning team includes community representation. Site Preparation: Existing infrastructure (current
WTP, school pumphouse, westend pumphouse) will be decommissioned and equipment removed from
these buildings. The building structures will likely stay in their current location(s) for repurposing or be
demolished, as agreed upon with the Nation. The new WTP will be installed in a currently undeveloped
plot of land, adjacent to the arena, located on the south side of Main Road within the community of
Sandy Bay. The site will be leveled through cut and fill. Gravel and/or another fill will be purchased and
delivered to site from an off-reserve source. Excavated material will be utilized to the extent possible.
Based on the Geotechnical Investigations conducted in March/April 2019, the need for blasting is not
anticipated as the testholes did not indicate bedrock presence. If required, it will be conducted by a
licenced contractor and utilize blast mats to mitigate flyrock. Construction – The contract for
construction will be tendered and a successful bidder will be chosen by SBOFN and the planning team.
Construction will occur in over a one-year period anticipated to start in Fall 2019. A Health and Safety
Plan will be developed to ensure that the active site does not become a hazard considering its central
location within the community. Operation – SBOFN will be responsible for the operation of the WTP
after commissioning is completed. The WTP is being designed to accommodate a projected population
of 8,001 people over the next 20 years. Decommissioning - Decommissioning is only planned for the
current WTP, school pumphouse, westend pumphouse. The new WTP is expected to be in operation for
at least 20 years.


Disclaimer

This map is for illustrative purposes. The markers represent the approximate locations based on available data. More than one marker may be identified for a given assessment.

 

Latest update

The assessment is in progress.

List all records

Contacts

Indigenous Services Canada
Dan Benoit, Sr Environmental Specialist
365 Hargrave Street
Winnipeg, Manitoba R3B 3A3
Telephone: 204-599-8579
Fax: 204-983-2936
Email: daniel.benoit@canada.ca


  • Location

    • Sandy Bay First Nation (Manitoba)
  • Project Type

    • Water Management
  • Status

    In progress
  • Start Date

    2020-11-27
  • Proponent

    Sandy Bay First NAtion
  • Authorities

    • Indigenous Services Canada
  • Assessment Type

    Project on federal lands
  • Reference Number

    81180

Nearby projects

..within 200 kilometres
Date modified: